The roof of the church is so impressive.
The tilers have been working all weekend and the roof is nearing completion. Here it is -
Meanwhile the rest of the building is moving along, the verandah roof has started, the aluminium doors and windows are now almost all fitted and the carpenter has been fitting the wooden door-frames.
The 'link' roof between the church and the kitchen has not yet been resolved, but Peter B has a plan!
The builders' holiday starts at the end of this next week, which will not really affect us as far as the labour goes - they will work on to Christmas Eve, and start again on the 3rd January - but the suppliers will be closing, which means that we will have to make sure that we have all the necessary materials on site by Friday to get us through to January.