On 12th April Angela Plekker, Mike Jahnig and John Cook met to review the original design and incorporating the construction methods recommended by Mike Jahnig, which had been endorsed at the meeting with Keith Alcock.
Mike proposed that we only build within areas of cut and this was possible for the whole of phase one. Cut material would be stock piled for land shaping and landscaping. It would also be used in control of stormwater for berms and creating localized attenuation dams.
With the amendments it is now possible to install the security fence in a gum pole and electric wire system very economically including a new sliding gate at the entrance. The meeting proposed this be carried out immediately following the recent attempted break in at the Church Office. Budget Estimate R 50,000.00 (Phase One only)
The foundations will be strip foundations, nominally reinforced only.